Gisborne was awarded the installation of both the 34’ diameter x 14’8” long SAG Mill and the 20’ diameter x 34’ long Ball Mill complete with motors, gears, associated lube systems, air systems and movable feed chutes, Gisborne also installed mechanical equipment and process piping in the concentrator and molybdenum process at the Gibraltar Mine Site just south of Williams Lake, BC.
Scope: Mechanical installation of both the Ball and SAG Mills, the equipment and process pipe installation in the concentrator and molybdenum process.