Project Details

CGT was awarded a contract with Dominion Diamond Ekati Corporation at their Diamond Mine in the NW Territories for the Ekati Fines HMS Plant CJ201 Structural, Mechanical, Piping, Electrical and Instrumentation Works.

Halfway through the onsite construction, due to a fire in the main plant area, our full team was re-directed to the repair and restoration of the plant. When this work was completed we transitioned back to the original project at the mine.

Scope: Demolition of the existing SDR plant foundations, installation of the new Fines HMS plant foundations and floor slab, erection of all structural steel including all flooring, hand rails, and plate work, installation of all mechanical equipment and all piping and accessories, completion of all electrical works including installing a new MCC, reconnecting existing cabling, and installing new cables, and the completion of all the instrumentation works.

  • Client Dominion’s Ekati Diamond Mine
  • Location Northwest Territories
  • Duration 9 months