We mobilized to site towards the end of 2018 and commenced work at the beginning of January 2019 with a projected completion of our scope toward the end of June 2019. Crews flew into Whitehorse then chartered to Mayo followed by a bus trip to the mine site.
Scope: Our scope of work included the installation of overland conveyors, pumps, tanks, clarifiers, kilns, filter presses, mechanical equipment, duct work and all related piping systems.